Phase 2 Construction | July Update

 

ON SITE
The foundation perimeters for Building 3 and 4 are laid out on site. Building 6 is up next, followed by Building 5.  Low-voltage utility relocation along the main roadway is underway to permit sub-grade preparation for Buildings 7 and 9. 

OFF SITE
The shop drawings are complete for all of the structural steel and fabrication is underway. Delivery for our lumber package has also begun. 

LOOKING FORWARD 
Starting next week, the crew will be pouring concrete for the Building 3 foundation. Several large landscaping trees will be brought on site this month and planted along our shared property line with the 4H Camp to help screen Building 5 views from existing 4H Camp infrastructure.